A milestone is within reach on Dogwood. We said goodbye to Ron's bulldozer this week. That is alway a big day, as the shaping work is essentially completed. The Team from TDI is hard at work putting the final touches on on the putting green surfaces in preparation for spins. Also, Dogwood 5 green complex is nearly completed. The sub grade has been completed and drainage installed. The gravel layer has been checked by Billy Fuller and the greens mix installation is ongoing. We plan to sprig greens on July 13th and as long as the weather holds out we will be able to grass all 9 holes!
|
Loading Ron's dozer |
|
Installation of drainage and gravel layer on Dogwood 5 green |
|
Team installing gravel layer on Dogwood 5 |
|
Green complex prep around Dogwood 9 in preparation for sod |
|
Floating out the putting surface on Dogwood 1 |
|
Final putting surface on Dogwood 5 |
|
Dogwood 5 green from tee. |