Monday, August 12, 2024

Topical Storm Debby

 Tropical Storm Debby paid us a visit this week.  Thankfully we didn't sustain too much wind damage, but we did end up with 12 inches of rain over a 4-day period.  Despite this enormous amount of rain, the golf courses held up beautifully.  The holes that have been grassed had some expected flooding around basins and some minor washouts around some bunker edges, but all in all the course handled the rain great.  The minor flooding we did have receded quickly and we were able to get back on the course to conduct debris cleanup by Friday.  We plan to mow out the course over the weekend and fertilize the course on Monday to help the soil recover from the flushing rain we had.

Palmetto 7, our last hole to grass did sustain some erosion of some soil, but its work the TDI team should quickly be able to repair and get back ready for grass.  The unfortunate issue will be the lost growing time on this hole from not being able to complete the sod work and prep the fairway for sprigs.  We will loose 2 weeks of growing time, as we anticipate planting to now occur on August 20.  Let's hope we have a warm September.  We will sprig this fairway heavier than the others have been to encourage a faster grow in.  We will also treat this hole with additional fertility and topdressing to push the grass as much as we can.  



Tree damage on Palmetto 4

Flooding on Palmetto 5

Flooding on Palmetto 4

dumping water through weir gate on palmetto 8

Greens handled rain beautifully

water draining through new basin

Washouts on Palmetto 7 fairway

minor bunker edge washouts


Thursday, August 1, 2024

Sprigging continues

 We are down to our last hole to grass.  Palmetto 8 was sprigged this week, leaving only Palmetto 7 to grass.  We hope to complete number 7 by end of next week, but the tropics are not looking good.  We will be taking some preventative steps to protect the turf we have on the ground ahead of the forecasted rain.  Sod work down the left edge of Palmetto 7 will also be completed by end of the week to wrap the bunkers and cover up the slopes between the fairway and the cart path.

Greens sprigs are starting to really fill in.  Routine mowing and spraying is ongoing and we plan to begin taking heights down some to help push lateral growth.  We will continue weekly fertlity applications and topdressing to encourage growth.  We are thrilled with the state of all the greens on Palmetto as we move into August.



Palmetto 1 Green

Mowing Palmetto 1 green

Fertility application to greens

Palmetto 8 grassing complete

Sod work on the left side of Palmetto 7

Sod work on left side of Palmetto 7

watering sprigs

Watering sprigs 

Sprigging Palmetto 8 Fairway

Sprigging Palmetto 8 fairway

The final push

 TDI has completed their punch list projects and has begun to demobilize their equipment.  This is always an exciting time as we wrap up the...